Sunday, March 16, 2014

Here is the finished product (99% anyway)

We got landscaping done. Things are cleaned. Driveway done.  Loving the new house.   Had a couple friends over... Great times.  We also give free tours for our friends who are interested.  

It's been a crazy ride.  We actually finished in six months.  Not bad for nonprofessional builders.  :).   I still hope to never do it again... But I'm sure we will.

Thanks for reading.  Greg

Wednesday, January 29, 2014

SNOW DAY!

Wow.  We got snow.   I came home right before lunchtime Tuesday - what a great day to be in the new house.   The kids are really enjoying things.  Lots of room for their toys - and so many toys got unpacked from storage that it's like Christmas all over again.

We have a lot of gradework and we have the driveway that still needs to be paved - but we'll have to warm up first a little bit.   really thankful that this didn't hold us up from moving in.   Knox Co. Codes were really great to us.




Monday, January 27, 2014

WE FINALLY MOVED IN!!!

Our first night at the house was on Monday, 1/27.  We got our occupancy approved on Friday and Shae got movers on the schedule for Monday.   We worked really  hard and got everything moved over, and Monday was our first night in the new house!!     It was a lot of fun.




Monday, January 13, 2014

Tiled kitchen backslpash!!


Wow.  This weekend we tiled the backsplash in the kitchen.   It was an all day job on Saturday ... like, 11 hours.   We got it done and it looks great.   It's a grey glass tile.   Was very frustrating to cut.   I don't look forward to the next time we get to work with glass.

Sunday we cleaned the house - top to bottom.  Vacuumed and mopped floors and changed air filters.  We will probably have to do it again ... but, it's the first step to getting all of the construction dust out.

We are eagerly waiting good weather so that we can get the driveway and patios poured.




Sunday, January 5, 2014

Wood Floors going in

We have worked like crazy.   I am so tired.  But, after heat turned on Friday - we started wood floors on Saturday/Sunday.  We finished Sunday evening.    I bought a nail gun from Amazon and it's been working awesome ... we're now professional wood floor layers.  :)

Below is the view from the kitchen area through the dining room towards the front door.


Here is the view through the kitchen into the nook. 
Check this out ... lol - view from the living room to the front door 
 

Friday, January 3, 2014

We finally got GAS turned on!

So, really excited - KUB just showed up to put the gas meter in.   Our HVAC peeps failed inspection a few times ...   so- now we can get warmed up and get the main heat on.


So, when the contractor got there to dig things out - "One Call" apparently mismarked the water line and they busted into the line.  Torrents of water exploded everywhere.   KUB showed up and fixed the leak.  Water was out all up the subdivision.